Works here at the Wild Dog Valley Road landslip site just a big excavation at this stage

Well, after well over 12 months the landslip sites of 2019 are nearing completion.

Best looking site so far would be the Griggs Road site and probably because this has the most affected locals needing access through this access point. The other two sites can be avoided on reasonably good other roads.

Griggs Road landslip site showing the pile formations retaining wall
Griggs Road landslip site showing the upper embankment stabilizing works in progress
What it looked like before repairs began
Mount Eccles landslip site road nearly completed and upper retaining walls in progress
What it looked like earlier
And it kept sliding until they started the repair works